How do I value work in progress for my building company?

In short: For a part-finished contract at the year end, your accounts recognise the share of the contract price earned so far, measured by how complete the job is, with the matching costs.

For small or short jobs, many builders instead carry the costs to date as work in progress, at the lower of cost and what they will recover.

Why does work in progress matter for tax?

Because Corporation Tax follows the accounts (CTA 2009 s46). If you leave out a half-finished job, the costs you have spent on it reduce this year’s profit, and the income lands next year. That understates this year’s profit. HMRC expects work in progress to be valued properly.

A worked example

A building company’s year ends on 31 March. It is halfway through a £150,000 extension. Costs to date are £60,000, and the total expected cost is £120,000.

Two ways of reflecting the job at 31 March
Stage of completionWork in progress at cost
How complete£60,000 ÷ £120,000 = 50%
Turnover recognised this year£75,000£0
Costs charged this year£60,000£0 (carried forward as WIP)
Profit this year£15,000£0
Profit next year£15,000£30,000

Long contracts that span a year end are normally accounted for by stage of completion, as in the first column. The cost method is common for short jobs, and it must never value WIP above what you expect to recover. If a job is heading for a loss, the expected loss is recognised straight away.

Running the business as a limited company?

Year-end accounts and the Company Tax Return are £199 one-off if you are not VAT registered with turnover up to £90,000, or £499 one-off if you are VAT registered or above £90,000. Bookkeeping is included.

See limited company prices

Get started

What goes into the cost?

  • Materials used on the job.
  • Subcontractor invoices for the job (gross, before any CIS deduction).
  • Direct labour on the job, including your employees’ wages and employer NI.
  • Plant hire for the job.
  • Not general overheads such as office costs or marketing.

Common mistakes

  • Leaving part-finished jobs out entirely.
  • Valuing WIP at the full contract price before the work is done.
  • Double counting: invoicing a stage payment and also carrying the same costs as WIP.
  • Ignoring a job that will make a loss.

Common questions

Is a stage payment already invoiced still WIP?

No. Work you have invoiced is turnover. WIP is only work done but not yet invoiced.

Do sole trader builders need WIP?

On traditional accounting, yes. On the cash basis, generally not.

What about materials on site not yet used?

They are stock or WIP at cost, not an expense of the year.

How Wenzo can help

Only you know how far each job has got, so a short year-end job list from you is the key document. Wenzo prepares year-end accounts and the Company Tax Return for £199 one-off (not VAT registered, turnover up to £90,000) or £499 one-off (VAT registered or above £90,000), with bookkeeping included. You approve everything before we file.

Article reviewed

Also asked as: “work in progress construction year end”, “how to value WIP for building jobs” or “part finished jobs at year end tax”.

NextWhen does my building company pay tax on retentions?

Need help with your annual accounts?

Call or WhatsApp us for a free, no-obligation chat. Send what you have, even if it’s incomplete.

Call 020 7123 9335
WhatsApp us

Mon to Sat, 9am to 9pm